Irrigation Update 5/31/22




We're continuing with the main line installation. We've completed hole 18 and have moved on to hole 1. We're also currently working on finishing the 12" pipe installation that leads to the pump house. This is an area with a lot of rock which have slowed the process in this area. We're also beginning to install some lateral pipes and sprinkler heads. We're testing the process in 11 approach. We anticipate moving up to 11 fairway on Wednesday if the weather cooperates. Once we begin the lateral installation, the hole will have to be closed. There will be signs posted on the tee box regarding handicap and scoring. We anticipate hole 11 being closed for the next two days.